Four aging council maisonettes were replaced with 15 energy efficient new council homes consisting of 3 new homes and 12 apartments with designated parking.
Build Programme
Demolition & remediation: | Q3 2019 |
---|---|
Start on site construction: | Q4 2019 |
First new homes complete: | Q1 2021 |
Build completion: | Q1 2021 |
Sustainability Features
- Photovoltaic solar panels and a green roof included in the design of the apartments.
- A bug hotel has been incorporated into the project to provide shelter for insects, and we planted 21 new trees and seeded wildflower meadows.